Georgia Roof Guide

How much should roof flashing overlap?

Short answer. Each piece of step flashing should be at least 2 inches longer than the shingle exposure so it overlaps the piece below by about 2 inches, and the code requires step flashing legs of at least 4 inches on the wall and 4 inches on the roof. Drip edge sections must overlap at least 2 inches, and every lap must run upper piece over lower piece.

Step flashing

Drip edge

Valleys

For open valleys lined with metal, the code requires the lining to be at least 24 inches wide. Where valley metal pieces join, the upper piece laps over the lower one by at least the manufacturer's minimum, and many installers add sealant in the lap. Closed valleys can be lined with a 36-inch roll or a self-adhering membrane.

Counterflashing and walls

Counterflashing on a chimney should lap down over the vertical leg of the step flashing far enough to cover it fully without being nailed through it, with its top edge set into a mortar joint. On sided walls, the housewrap and siding lap over the step flashing's wall leg, and the siding should stop slightly above the roof surface so it does not wick water.

Always check the shingle wrapper and local requirements, since Georgia uses the 2024 IRC with state amendments as of January 1, 2026. See roof flashing explained and drip edge explained.

In depth

Why do chimneys leak, and when does a chimney need a cricket?How chimneys leak through flashing, brick and crowns, what Georgia's code says about crickets on wide chimneysShould you replace skylights when you replace the roof?Why a roof replacement is the best time to replace or reflash skylights, what warranties require, energy criteWhy do pipe boots leak, and how are they fixed?How plumbing vent pipe boots fail on Georgia roofs, the installation mistakes behind most leaks, repair collar

People also ask