What is involved in changing the pitch of an existing roof?

Short answer. Changing the pitch of an existing roof follows a construction sequence: design and engineering, permits and HOA approval, tear-off, new framing, sheathing and roofing, then exterior and interior finish work, with inspections along the way. The roofing itself is one of the last and shortest steps.

The sequence

  1. Define the goal. More attic space, better drainage, or a new look. The goal decides how steep and how much framing changes.
  2. Design and engineering. An architect or engineer specifies rafters or trusses, wall connections, and any beams, and checks that the walls and foundation can carry the new loads.
  3. Permits and approvals. Structural roof changes require a building permit in Georgia jurisdictions, and HOAs often review exterior changes. Zoning height limits can also apply. See roofing permits in Georgia.
  4. Order materials. Engineered trusses often take weeks to build, so they are ordered before demolition starts.
  5. Demolition and weather protection. Roofing and framing come off in planned sections, with tarps ready for Georgia's pop-up afternoon storms.
  6. Framing. New trusses or rafters are set, braced, and tied down with the specified hardware, then the framing is inspected.
  7. Sheathing and roofing. Deck, drip edge, underlayment, leak barrier, flashing, shingles, and ridge ventilation go on. Balanced intake and exhaust matter in the new attic; see roof ventilation basics.
  8. Exterior finish. New fascia, soffits, gutters, and siding on the taller gable ends.
  9. Interior and insulation. Ceilings, ducts, and attic insulation. ENERGY STAR suggests about R-49 for most of Georgia and R-60 in the north.
  10. Final inspections.

Time and disruption

Expect weeks rather than days, with the home partly exposed during framing. That is very different from a standard replacement, which on an average roof usually takes a day.

In depth

Can you put new shingles over old ones in Georgia?Georgia's code allows one shingle layover in limited cases, never over two layers. Learn the rules, manufacturShould you replace your roof before installing solar panels?Solar panels outlast many Georgia shingle roofs. How to weigh roof age against panel life, reinstall costs, waWhat happens on roof replacement day?What really happens when a Georgia roof is replaced: prep, tear-off, deck repairs, flashing, nailing, crew saf